San Bernardino Transit Center Celebrates One Year of Service

wp-1473652650531.jpg
One artist used Omnitrans’ old logo as part of his drawing. Photo: author/iNLand fIEts.

This past Saturday, visitors to the San Bernardino Transit Center (SBTC) were treated to a tunes, a cold drink, and a place to rest between buses as Omnitrans held a party to celebrate the first year of operations of the SBTC. As local all-girl band Alive in the Lights rocked out under a cloudless sky, members of the community participated in a chalk art contest in the plaza in front of the SBTC. Artists were competing for a $250 grand prize and they brought their A-game with many great designs. As they drew, they were entertained by antics provided by the SANBAG See Tracks, Think Train campaign mascot  out spreading the word of practicing safety around tracks.

A little over year ago, on August 24, 2015, that dignitaries and curious onlookers stopped by the soon-to-be-completed SBTC in the eponymous city to celebrate the grand opening of the new transfer and customer service facility. The anticipation turned to excitement on September 8, when the SBTC officially opened to the public. Envisioned by Omnitrans since the 1980s, the Transit Center replaces the transfer hub that had floated around the 4th St. area of downtown San Bernardino for decades.

It brings together almost all of their East Valley service into one central location, providing connections to the sbX Green Line, MARTA Off the Mountain service, VVTA BV Link, (as of today) Pass Transit Commuter Link 120, Metrolink by the end of next year via the under construction Downtown Passenger Rail Project, and the Redlands Passenger Rail Project which is projected to be open by 2021. However, the coordination to ensure those connections are available and make sense did delay the completion of the TC, which was originally supposed to open before or at least in conjunction with sbX. At some point in the distant future, CA high-speed rail may also arrive at the site, which would truly awaken the city.

The facility has a staffed customer service desk and 24/7 security to maintain peace and order. Omnitrans has thus far received largely positive reviews of the facility from the riders, many of whom really appreciate the fact that there is an indoor waiting area, public bathrooms, and connections all in one place. The lobby isn’t a grand hall, but it’s design is functional and elegant and provides travelers a much-needed respite from the elements, especially those who are waiting for connections to Omni’s services that run at only an hourly frequency.

However, not everyone is completely happy with the TC. In addition to the usual complaints about the use of tax dollars for public transit, several people have expressed concern about the lack of parking provided at the site. This is certainly an interesting argument because, realistically speaking, there are few instances where Omnitrans’ local service provides a travel time that is superior to that of driving and most of them are not really in the areas around downtown San Bernardino. As such, it doesn’t seem very likely that many people would drive to park and take the bus, something which is already borne out by the parking lots that Omnitrans built for the sbX Green Line that are 99% empty 99% of the time. Building another lot at the TC for bus passengers doesn’t seem necessary and Omnitrans was right to not do so.

wp-1473652641726.jpg
In the future, Omnitrans hopes to bring a transit-focused development to the empty lot seen behind the canopies.

Not doing so also meant that they have space that is available for development on the site that will be easier to convert to that use from an empty lot than it would be from a designated parking lot. However, since the TC is also going to connect to Metrolink, parking will be provided in conjunction with the completion of that portion of the project. Additionally, 10-minute drop-off parking is available on Rialto Ave. at the front of the TC. Furthermore, there are literally dozens of acres of surface lots available within a two block radius of the site that could be tapped with some sort of agreement to provide parking for the TC if it’s truly necessary, including over 13 acres directly adjacent the TC at the San Manuel Stadium.

While parking for cars at the TC isn’t plentiful, there is a decent amount of bike parking strewn around the site, albeit of mixed utility. The good part about it is that it is of an inverted U shape and square, but unfortunately, the racks themselves were installed far too close together, rending them partially useless. In addition to the bike parking, the TC is also host to the San Bernardino Bike Hubitat co-op shop. Since opening in May, the Hubitat has helped hundreds of Omni patrons continue rolling.

In the next few years, the SBTC should see an increase in use as more transit connections come online. However, most of the ultimate success for the Center rests squarely on the shoulders of the City. As they look to exit bankruptcy, they have the opportunity to really become a regional powerhouse and world-class city with smart investments and leadership. The coming transit connections provide an extremely advantageous starting point, but they still need to really take the reigns and look forward to the future. Hopefully, that realization happens soon and we can look forward to many more anniversary celebrations.

Progress Report: Downtown San Bernardino Passenger Rail Project

Work is humming along on SANBAG’s project to extend Metrolink service from the current terminus at San Bernardino’s Santa Fe Depot to the Transit Center in downtown San Bernardino. This move of a little over a mile will bring new options and connections to transit users from San Bernardino and many surrounding communities. Though it opened last year, the Transit Center currently only has connections with fixed route bus and BRT service. Once open, this project will provide the first passenger rail service to downtown San Bernardino in at least 70 years.

OLYMPUS DIGITAL CAMERA
The switch that will be installed just north of Rialto Ave. is under construction. All photos: author.

Over the last year or so, the construction phase of this project has been ongoing, with changes slowly manifesting themselves all through San Bernardino’s Lytle Creek neighborhood. By far, the biggest changes are of the transportation right-of-ways. The DSBDPRP is double-tracking the entire loop from the Short Way Subdivision, through the BNSF San Bernardino yard past the Santa Fe Depot, then onto [what remains of] the Redlands District to just past G St., where it splits to provide a third track at the Transit Center and otherwise rejoins the existing double-track segment. The double-tracking will allow trains to freely flow from the Transit Center to the yard that is located about two route miles away in Colton.

In addition to the double-track, two grade crossings are being closed by the project: 3rd St. at the tracks and I St. south of the tracks (the intersection with Rialto from the north remains as a right in/out). The closures aren’t completely bad as especially with I St., it provides a great opportunity for a modernization project on an otherwise chronically overbuilt street. However, it appears that they closures will also cut the neighborhood access off, so that is a bit of a loss to the community.

OLYMPUS DIGITAL CAMERA
One of the cross tracks from the Colton Crossing embedded in front of the Santa Fe Depot.

The Santa Fe Depot itself is also seeing some upgrades. The project is rebuilding the passenger boarding experience to be run-through to allow all trains to be able to continue on to the Transit Center. This includes an overpass of the tracks. But there have been other changes to the outside. Most significantly, the area in front has been altered to more parking away from directly in front of the building to showcase the entrance and really give a more stately look to the building. A nice walkway now leads directly to the front door and a crossover from the Colton Crossing has been embedded in the concrete directly in front of the building. There is also a pad and stop for the Amtrak Thruway bus service that makes daily stops at the station.

OLYMPUS DIGITAL CAMERA
The completed switch awaits installation as work on the second track continues.

Finally, farther west, work has begun on the full extent of the double-tracking. Just north of Rialto Ave., workers have been putting together the switch that will provide the start of the double-track segment that goes through to the Transit Center. Additionally, fencing has been installed at the end of King St. to seal the corridor and keep people off the tracks. While the IEOC Line is the only scheduled Metrolink service to use the Shortway Sub, it is also the connection to the yard, so nearly 50 trains per day will pass through the area to reach the yard in Colton.

Ideally, there will be no major snafus as the year winds down and soon after we ring in the new year, we can begin to take advantaged of one of the most important transit connections in the Inland Empire. Already three years behind, it can’t open a moment too soon. In tandem with the coming Redlands Rail, mobility options in the East Valley are really set to be substantially improved. Hopefully, the cities in the region will be willing and able to properly manage the opportunity that they’re being handed.